Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

WD-2923 (formerly WD-2764): 24-inch Water Main Rehabilitation from University Mound Reservoir to 3rd St

0% in published scope

SFPUC · Sewer, water or power · Construction · Under way, ends 1 Jun 2027

All 4 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
Bacon St, Egbert Ave, Neptune St, Phelps St, Thornton Ave, Williams Ave
Planned bikeway
Shared street, 0.3 mi on Williams Ave
Would reach
2,077 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 4 street segments that lack one. Closer in: 1,830 residents with none within about one block (440 feet) today would have one; 3,427 residents with none within about two blocks (880 feet) today would have one
Scope
“Rehabilitating 24-inch on Bacon Street from San Bruno Ave to Bowdoin, Phelps from Egbert to Williams St, and on Williams from Phelps to 3rd St”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionDec 2024Jun 2027
Sources disagree
The coordination feed gives construction starting 2024-12-16; SFPUC's project page text gives 2026-07 (“July 2026”).
The coordination feed gives construction ending 2027-06-01; SFPUC's project page text gives 2027-10 (“October 2027”).
Records
SFPUC project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

3 decisions on the same streets, not naming this project

Construction on these street segments

202220232024202520262027202820292030todayWD-2923 (formerly WD-2764): 24-inch …Bayview Community Based Transportati…PW StreetResurfacingPro-BBSR Pavemen…Various Locations Sewer Replacement …PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27: construction 1 Jul 2026 to 7 Jul 2027Various Locations Sewer Replacement No 39: construction 15 May 2028 to 14 Nov 2029Bayview Community Based Transportation Plan: construction 2022 to end not publishedWD-2923 (formerly WD-2764): 24-inch Water Main Rehabilitation from University Mound Reservoir to 3rd St: construction 16 Dec 2024 to 1 Jun 202716 Dec 2024 – 1 Jun 2027from 20221 Jul 2026 – 7 Jul 202715 May 2028 – 14 Nov 2029

Construction start and end as each department publishes them; a dot where only one is published.

3 other projects on these street segments