SF WorksMobility Improving The Bike Network Improving The Bike NetworkSafer School Trips Current Repaving Projects Other Bike PlansCurrent Repaving Projects

Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

FASIP - Western SOMA and Northern Mission District Sewer System

0% in published scope

SFPUC · Sewer, water or power · Design · Under way, ends 31 Jan 2027

The project's one street segment on a planned bikeway street already has an all-ages bikeway.

Streets
11th St, 14th St, Erie St
Planned bikeway
Separated bikeway, 0.24 mi on 11th St
Scope
“Categorical exemption”
Dates
StartEnd
Public consultationDecember 2December 2
ConstructionFeb 2026Jan 2027
Sources disagree
The coordination feed gives construction starting 2026-02-01; SFPUC's project page text gives 2023 (“late 2023”).
The coordination feed gives construction ending 2027-01-31; SFPUC's project page text gives 2030 (“2030”).
The start date has passed (2026-02-01) while the phase is still Design, per the coordination feed.
Records
SFPUC project page · Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

2 decisions on the same streets, not naming this project

Construction on these street segments

20232025202720292031203320352037todayFASIP - Western SOMA and Northern Mi…PW FOLSOM AREA STORMWATER IMPROVEMEN…PW As Needed Spot Sewer Replacement …11th Street Safety Improvements Proj…Various Locations Pavement Renovatio…Western SOMA and Northern Mission Di…Various Locations Pavement Renovatio…PW FOLSOM AREA STORMWATER IMPROVEMENT PROJECT: construction 2023 to 31 Dec 2030PW As Needed Spot Sewer Replacement No 47: construction 22 Sep 2025 to 26 Oct 202611th Street Safety Improvements Project: construction 1 Jun 2026 to 21 May 2028Various Locations Pavement Renovation No 87: construction 13 Mar 2027 to 26 May 2028Western SOMA and Northern Mission Districts Sewer Replacement WW-719D: construction 27 Jun 2027 to 30 Mar 2029Various Locations Pavement Renovation Under Overhead Contact System No 4: construction 2 Feb 2035 to 16 Apr 2036FASIP - Western SOMA and Northern Mission District Sewer System: construction 1 Feb 2026 to 31 Jan 20271 Feb 2026 – 31 Jan 20272023 – 31 Dec 203022 Sep 2025 – 26 Oct 20261 Jun 2026 – 21 May 202813 Mar 2027 – 26 May 202827 Jun 2027 – 30 Mar 20292 Feb 2035 – 16 Apr 2036

Construction start and end as each department publishes them; a dot where only one is published. 2 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.