Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

Mission, 8th, 9th, Howard and Natoma Brick Sewer Rehabilitation

0% in published scope

Public Works · Sewer, water or power · Construction · Under way, ends 31 Oct 2026

2 of the project's 11 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
10th St, 11th St, 7th Ave, 8th St, 9th St, Carl St
Planned bikeway
Separated bikeway, 0.79 mi on 8th St, 7th Ave, Howard St, Fell St
Shared street, 0.26 mi on 7th Ave
Would reach
346 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 1,126 residents with none within about one block (440 feet) today would have one
Scope
“1223i WW-754 West SOMA, Panhandle & Inner Sunset Sewer Improvments”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionAug 2025Oct 2026
Records
SFPUC contract page (WW-754 West SOMA, Panhandle, and Inner Sunset Sewer Improvements) · Interagency coordination feed record (DataSF row)

City decisions naming this project

9 decisions on the same streets, not naming this project

Construction on these street segments

2024202520262027202820292030todayMission, 8th, 9th, Howard and Natoma…Folsom-Howard Streetscape Project8th, Beale, Clay, Leavenworth and Ma…8th St, Clay St and Leavenworth St P…Bikeway HardeningWest SoMa, Panhandle and Inner Sunse…Folsom-Howard Streetscape Project: construction 2024 to 31 Dec 20298th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation): construction 3 Feb 2025 to 27 Oct 20268th St, Clay St and Leavenworth St Pavement Renovation and Sewer Replacement: construction 3 Feb 2025 to 27 Oct 2026Bikeway Hardening: construction 1 Jul 2025 to 30 Jun 2027West SoMa, Panhandle and Inner Sunset Large Sewer Improvements Project: construction Oct 2025 to 30 Nov 2026Mission, 8th, 9th, Howard and Natoma Brick Sewer Rehabilitation: construction 11 Aug 2025 to 31 Oct 202611 Aug 2025 – 31 Oct 20263 Feb 2025 – 27 Oct 20263 Feb 2025 – 27 Oct 20261 Jul 2025 – 30 Jun 2027Oct 2025 – 30 Nov 20262024 – 31 Dec 2029

Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.

8 other projects on these street segments