Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
Mission, 8th, 9th, Howard and Natoma Brick Sewer Rehabilitation
0% in published scope
Public Works · Sewer, water or power · Construction · Under way, ends 31 Oct 2026
2 of the project's 11 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 10th St, 11th St, 7th Ave, 8th St, 9th St, Carl St
- Planned bikeway
- Separated bikeway, 0.79 mi on 8th St, 7th Ave, Howard St, Fell St
Shared street, 0.26 mi on 7th Ave - Would reach
- 346 residents (2020 census) would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 2 street segments that lack one. Closer in: 1,126 residents with none within about one block (440 feet) today would have one
- Scope
- “1223i WW-754 West SOMA, Panhandle & Inner Sunset Sewer Improvments”
- Dates
Start End Public consultation not published not published Construction Aug 2025 Oct 2026 - Records
- SFPUC contract page (WW-754 West SOMA, Panhandle, and Inner Sunset Sewer Improvements) · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Award Contract No. WW-754, West SOMA, Panhandle, and Inner Sunset Sewer Improvements, to responsible bidder that submitted the lowest responsive bid, Precision Engineering, Inc., in the amount $17,912,054 and with a dura…13 May 2025 · SFPUC Commission · approve the Consent Calendar
9 decisions on the same streets, not naming this project
- Award Grant Agreement No. PRO.0300 (G), Demonstration Garden Programming and Maintenance to Earth Island Institute, acting as the fiscal sponsor for Garden for the Environment, to operate a public demonstration garden an…11 Mar 2025 · SFPUC Commission · approve the Consent Calendar Item Nos. 6a, 6b, and 6c
- Award Contract No. WD-2844, 12-Inch Ductile Iron Water Main Installation on Parnassus Avenue, from Stanyan Street to 6th Avenue, on Lawton Street from 7th Avenue to Funston Avenue, and Various Street Locations, to the re…24 Sep 2024 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – BLUE ZONE 11th Street, west side, from 15 feet to 40 feet south of Folsom Street 11(b). ESTABLISH – GENERAL LOADING ZONE, 5 MIN, AT ALL TIMES, DAILY Folsom Street, south side, from 56 feet to 116 feet west of…2 Aug 2024 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Award Contract No. WW-743, Geary Boulevard Sewer and Water Improvements Phase 2, to the responsible bidder that submitted the lowest responsive bid, Cratus, Inc., in the amount of $45,957,035, and with a duration of 1,03…25 Jun 2024 · SFPUC Commission
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Fell Street, south side, from 30 feet to 102 feet east of Clayton Street (72-foot station) (Supervisor District 5) (Approvable by the City Traffic En…5 Jan 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Accept work performed by D’Arcy & Harty Construction, Inc for Contract No. WW-712, New Montgomery, Jessie, Minna, and Mission Street Brick Sewer Rehabilitation, for a total contract amount of $6,891,778, and with a total…9 May 2023 · SFPUC Commission · approve the Consent Calendar
- Approve an increase of $2,250,000 to the contract cost contingency, and an increase of 180 consecutive calendar days to the contract duration contingency for Contract No. WW-712, New Montgomery, Jessie, Minna, and Missio…8 Feb 2022 · SFPUC Commission · approve Item 10
- Approve an increase of 30 consecutive calendar days to the contract duration contingency for Contract No. WW-703, Mission Street, 16th to Cesar Chavez Street, Brick Sewer Rehabilitation; and authorize the General Manager…14 Dec 2021 · SFPUC Commission · approve Consent Calendar items 10a through 10g
- Approve the plans and specifications, and award Contract No. WW-712, New Montgomery, Jessie, Minna, and Mission Streets Brick Sewer Rehabilitation, in the amount of $4,888,750, and with a duration of 390 consecutive cale…11 May 2021 · SFPUC Commission · approve Consent Calendar items 8c, 8d, and 8g
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- West SoMa, Panhandle and Inner Sunset Large Sewer Improvements ProjectSFPUC · Construction · 16 shared street segments
- PW Mission SoMa Impr Pvmt RenoPublic Works · Design · 13 shared street segments
- 7th Street and 8th Street Safety ProjectsSFMTA · Completed · 11 shared street segments
- 8th, Beale, Clay, Leavenworth and Main Streets Sewer Replacement (JV w 8th St, Clay St and Leavenworth St Pavement Renovation)Public Works · Construction · 8 shared street segments
- Castro St and Divisadero St Pavement Renovation ProjectPublic Works · Planning · 5 shared street segments
- Folsom-Howard Streetscape ProjectSFMTA · Current · 4 shared street segments
- 8th St, Clay St and Leavenworth St Pavement Renovation and Sewer ReplacementPublic Works · Construction · 4 shared street segments
- Bikeway HardeningSFMTA · Planning · 3 shared street segments
How we built this: About the Data