252 street projects under way or coming up on the Biking and Rolling Plan's network.
Various Locations Pavement Renovation No 81 and Sewer Replacement
0% in published scope
Public Works · Repaving · Construction · Under way, ends 31 Aug 2027
1 of the project's 2 street segments on planned bikeway streets lacks the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- Alhambra St, Avery St, Buchanan St, California St, Capra Way, Ellis St
- Planned bikeway
- Shared street, 0.28 mi on Francisco St, Alhambra St
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Jan 2026 Summer, 2027 - Sources disagree
- The coordination feed gives construction ending 2027-05-16; Public Works' project page (Completion “Summer, 2027”; text “Summer, 2027”), 2027-08-31, which is shown.
- Records
- Public Works project page · Interagency coordination feed record (DataSF row)
City decisions naming this project
- Various Locations Pavement Renovation No. 81 and Sewer Replacement – Contract Award to Esquivel Grading & Paving, Inc in the amount of $5,083,488.3125 Sep 2025 · Public Works Commission
6 decisions on the same streets, not naming this project
- Accept work performed by M. Squared Construction, Inc., under Contract No. WD- 2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street; approve Modification No. 3 (Final) dec…10 Nov 2025 · SFPUC Commission · approve the Consent Calendar
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Post Street, south side, from 23 feet 9 inches to 43 feet 9 inches east of Pierce Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Grant Brokl, [st…17 May 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Award Contract No. WD-2896, 12-Inch Ductile Iron Water Main Installation on Webster Street from Grove Street to Eddy Street, to the responsible bidder that submitted the lowest responsive bid, M. Squared Construction, In…9 Jan 2024 · SFPUC Commission · approve items 6a through 6i
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Buchanan Street, east side, from 22 feet to 85 feet north of Lombard Street (63-foot station) (Supervisor District 2) (Approvable by the City Traffi…22 Sep 2023 · Engineering hearing · On hold pending exploration of a Moscone Park site as requested by the Supervisor.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Post Street, north side, from Baker Street to 88 feet easterly (75-foot bike share station with red zones on either side) (Supervisor District 5) Pro…12 Jun 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in opposition.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Post Street, north side, from 14 feet to 99 feet west of Webster Street (84-foot bike share station with red zones on either side) (Supervisor Distri…24 Jan 2020 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 6 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Western Addition Community Based Transportation Plan ImplementationSFMTA · Current · 21 shared street segments
- PW Various Locations Sewer Replacement (JV VL PR No 81)Public Works · Construction · 10 shared street segments
- WD-2936 8-, 12- & 16-inch Ductile Iron Water Main Replacement on Geary Boulevard from Stanyan Street to Presidio Avenue & on Post Street from Presidio Avenue to Scott Street & on Various Side StreetsSFPUC · Design · 7 shared street segments
- Western Addition Area Traffic Signal Upgrades Phase 2SFMTA · Design · 3 shared street segments
- Western Addition Traffic Signal Upgrades Phase 2Public Works · Design · 3 shared street segments
- Octavia Boulevard Enhancement ProgramSFMTA · Current · 3 shared street segments
- Scott St & Ellis Stother · Planning · 3 shared street segments
- PW Various Locations Sewer Replacement No 31Public Works · Design · 1 shared street segment