252 street projects under way or coming up on the Biking and Rolling Plan's network.
Geneva Ave and Sloat Blvd Pavement Renovation
0% in published scope
Public Works · Repaving · Planning · Starts 29 Dec 2029, ends 13 Mar 2031
22 of the project's 29 street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.
- Streets
- 42nd Ave, 44th Ave, 46th Ave, Brookdale Ave, Carrizal St, Carter St
- Planned bikeway
- Separated bikeway, 2.5 mi on Sloat Blvd
Shared street, 2.2 mi on Geneva Ave
Bikeway of undecided type, 0.24 mi on Santos St - Would reach
- 6,225 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 22 street segments that lack one. Closer in: 3,120 residents with none within about one block (440 feet) today would have one; 4,367 residents with none within about two blocks (880 feet) today would have one
- Scope
- None published.
- Dates
Start End Public consultation not published not published Construction Dec 2029 Mar 2031 - Records
- Interagency coordination feed record (DataSF row) · No Public Works page for this job; closest official source: Public Works paving map
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
10 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Sloat Boulevard, south side, from 47th Avenue to 57 feet westerly (in the buffer adjacent to the two- way bikeway) (Supervisor District 7) (Approvabl…12 Jun 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Sloat Boulevard, north side, from 10 feet to 20 feet east of 45th Avenue (Supervisor District 4 and 7) (Approvable by the City Traffic Engineer) Grant Brokl, [staff email …17 May 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve an increase of 115 calendar days to the contract duration contingency for Contract No. WW-684, 45th, 46th, 47th Aves, Vicente and, Wawona Streets, and Sloat Blvd Sewer Replacement, with Precision Engineering, Inc…26 Mar 2024 · SFPUC Commission · approve items 6a through 6e
- ESTABLISH – CLASS IV BIKEWAY Sloat Boulevard, eastbound and westbound, from 47th Avenue to Skyline Boulevard (two-way protected bikeway on south side of roadway)* 10(b). RESCIND – CLASS II BIKEWAY Sloat Boulevard, eastbo…16 Jun 2023 · Engineering hearing · Lengthened and relocated taxi zone and adjusted passenger loading and blue zone locations based on public hearing feedback. Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 44th Avenue, east side, from Judah Street to 60 feet southerly (52-foot bike share station with red zones on either end) (Supervisor District 4) (App…6 Jan 2023 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- Approve the plans and specifications and award Contract No. WW-684, 45th, 46th, 47th Aves, Vicente, Wawona Streets and Sloat Blvd. Sewer Replacement, in the amount of $7,342,613, and with a duration of 375 consecutive ca…8 Nov 2022 · SFPUC Commission · approve the Consent Calendar, with the amendment to the date on the
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION 44th Avenue, east side, from Judah Street to 60 feet southerly (52-foot bike share station with red zones on either end) (Supervisor District 4) (App…18 Feb 2022 · Engineering hearing · Item withdrawn.
- Accept work performed by JDB & Sons Construction for Contract No. WW-611, Cutler Avenue, Lower Great Highway, Sloat Boulevard, and Wawona Street Sewer Replacement; approve Modification No. 6 (Final) decreasing the contra…23 Nov 2021 · SFPUC Commission · approve Consent Calendar items 10a, 10c, 10d, and 10e
- ESTABLISH - CLASS 2 BIKE LANE Geneva Avenue, both directions, between Prague Street and Brookdale Avenue Dusson Yeung, [staff email removed — see the order] (Supervisor Districts 10 & 11) Upgrade narrow shoulders to 5-fo…16 Apr 2021 · Engineering hearing · Approved by the City Traffic Engineer to forward to the SFMTA Board for final approval and implementation.
- Authorize the General Manager to execute a Project Partnership Agreement with the Army Corps of Engineers (ACOE) for the construction of the Ocean Beach Beneficial Use of Dredged Materials Project to place sand dredged f…23 Feb 2021 · SFPUC Commission · approve Consent Item 22
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 6 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Geneva Avenue Traffic Signal ProjectPublic Works · In progress · 15 shared street segments
- Visitacion Valley and Portola Community Based Transportation PlanSFMTA · Planning · 15 shared street segments
- Outer Sunset Traffic Management ProjectSFMTA · Completed · 14 shared street segments
- PG&E Power Asset AcquisitionSFPUC · Planning · 8 shared street segments
- Sloat Blvd Quick-Build ProjectSFMTA · Detailed Design · 7 shared street segments
- District 11-Wide Traffic Calming ProjectSFMTA · 7 shared street segments
- 8 Bayshore: Visitacion Valley Stop ImprovementsSFMTA · 3 shared street segments
- Sloat and Skyline Intersection ImprovementSFMTA · Completed · 2 shared street segments