Current Repaving Projects

252 street projects under way or coming up on the Biking and Rolling Plan's network.

← All projects

PW - M & J Lines - Muni Forward Project

0% in published scope

Public Works · Streetscape · Design · Under way, ends 1 Jan 2027

All 14 of the project's street segments on planned bikeway streets lack the all-ages bikeway the Biking and Rolling Plan calls for. Its published scope does not mention bikes.

Streets
19th Ave, Arch St, Baden St, Bright St, Broad St, Orizaba Ave
Planned bikeway
Shared street, 1.3 mi on Randolph St, 19th Ave, San Jose Ave
Would reach
3,665 residents (2020 census), 1 school would be newly within a quarter-mile walk of an all-ages bikeway if the planned bikeway were built on the project's 14 street segments that lack one. Closer in: 4,994 residents, 1 library with none within about one block (440 feet) today would have one; 4,250 residents, 1 school with none within about two blocks (880 feet) today would have one
Scope
“M & J Lines - Muni Forward Project”
Dates
StartEnd
Public consultationnot publishednot published
ConstructionDec 2023Jan 2027
Sources disagree
The coordination feed carries this job as 2 rows (row 31167 shares numbers 10038465 and 2454I with row 25702) that disagree: row 25702, Design, 2023-12-27 to 2027-01-01; row 31167, Design, 2026-12-31 to 2027-12-30. The dates shown are row 25702's.
The start date has passed (2023-12-27) while the phase is still Design, per the coordination feed.
Records
SFMTA project page · Interagency coordination feed record (DataSF row) · Interagency coordination feed record (DataSF row)

City decisions naming this project

None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.

1 decisions on the same streets, not naming this project

Construction on these street segments

20222023202420252026202720282029todayPW - M & J Lines - Muni Forward Proj…Broad Street and Randolph Street Sew…J Church Safety and Accessibility Pr…M Ocean View Transit and Safety Proj…Broad Street and Randolph Street Sewer Replacement: construction 15 Mar 2022 to 1 Feb 2028J Church Safety and Accessibility Project: San Jose Avenue: construction 29 Sep 2023 to 31 Dec 2027M Ocean View Transit and Safety Project: construction Apr 2024 to 30 Nov 2025PW - M & J Lines - Muni Forward Project: construction 27 Dec 2023 to 1 Jan 2027Apr 2024 – 30 Nov 202527 Dec 2023 – 1 Jan 202715 Mar 2022 – 1 Feb 202829 Sep 2023 – 31 Dec 2027

Construction start and end as each department publishes them; a dot where only one is published. 5 other projects on these street segments publish no construction dates.

8 other projects on these street segments

Data Sources

Projects and city records

The Biking and Rolling Plan

The bike network

Who it reaches

How we worked out the project list is on About the Data.