Current Repaving Projects
252 street projects under way or coming up on the Biking and Rolling Plan's network.
14-009 8-, and 24-inch Ductile Iron Water Main Replacement on Page Street from Stanyan to Fillmore Streets
Already built
SFPUC · Sewer, water or power · Design · Under way, ends 20 Jan 2027
All 14 of the project's street segments on planned bikeway streets already have an all-ages bikeway.
- Streets
- Cole St, Fillmore St, Page St, Steiner St
- Planned bikeway
- Shared street, 2.6 mi on Page St
- Scope
- “8-, and 24-inch Ductile Iron Water Main Replacement on Page Street from Stanyan to Fillmore Streets”
- Dates
Start End Public consultation not published not published Construction Jun 2025 Jan 2027 - Sources disagree
- The start date has passed (2025-06-01) while the phase is still Design, per the coordination feed.
- Records
- Interagency coordination feed record (DataSF row) · No SFPUC page for this job; closest official source: Water Main Replacement Process
City decisions naming this project
None found in SFMTA engineering hearings, the SFMTA Board, the Board of Supervisors, the SFPUC Commission, the Public Works Commission, the SFCTA Board or the Recreation and Park Commission records read through 2026-09-30.
13 decisions on the same streets, not naming this project
- ESTABLISH – NO STOPPING, EXCEPT BICYCLES ESTABLISH – BIKESHARE STATION Page Street, north side, from Fillmore Street to 20 feet easterly (in existing red zone) Fillmore Street, west side, from Page Street to 21 feet nort…24 Jul 2026 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – RED ZONE Steiner Street, west side, from 5 feet to 28 feet south of Grove Street northern crosswalk (23-foot zone, the rest of the intersection is already red zone) 8(b). ESTABLISH – NO PARKING ANY TIME, EXCE…16 May 2025 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO PARKING ANY TIME, EXCEPT BICYCLES Steiner Street, west side, from 10 feet to 20 feet north of Post Street (Supervisor District 5) (Approvable by the City Traffic Engineer) Grant Brokl, [staff email removed…17 May 2024 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Page Street, south side, from Cole Street to 70 feet easterly (Supervisor District 5) (Approvable by the City Traffic Engineer) Laura Stonehill, [sta…19 May 2023 · Engineering hearing · On hold for further outreach at this location and to investigate other potential locations.
- ESTABLISH – RIGHT OR LEFT TURN ONLY, EXCEPT BICYCLES Page Street, eastbound, at Masonic Avenue (Approvable by the City Traffic Engineer) 11(b). ESTABLISH – NO RIGHT TURN, EXCEPT BICYCLES Masonic Avenue, northbound, at Pa…8 Jul 2022 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Page Street, south side, from Masonic Avenue to 90 feet easterly (82-foot station with red zones either side) (Supervisor District 5) Daniel Carr, [s…4 Dec 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation.
- ESTABLISH – NO STOPPING EXCEPT BICYCLES ESTABLISH – BIKE SHARE STATION Fillmore Street, east side along median, from Jefferson Street to 53 feet southerly (bike share station in angled parking stalls) (Supervisor Distric…17 Jul 2020 · Engineering hearing · Approved by the City Traffic Engineer for implementation. Public Comments: Received comments in support and opposition.
- Motion directing the Clerk of the Board to prepare findings reversing the determination by the Planning Department that the proposed San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Pr…4 Feb 2020 · Board of Supervisors · Killed
- Motion conditionally reversing the determination by the Planning Department that the San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Project is categorically exempt from further envir…4 Feb 2020 · Board of Supervisors · Killed
- Motion affirming the determination by the Planning Department that the proposed San Francisco Municipal Transportation Agency Page Street Bikeway Improvements Pilot Project is categorically exempt from further environmen…4 Feb 2020 · Board of Supervisors · Passed
- Hearing of persons interested in or objecting to the determination of exemption from environmental review under the California Environmental Quality Act issued as a Categorical Exemption by the Planning Department on Sep…4 Feb 2020 · Board of Supervisors · Filed
- Approving a 15-month Page Street Bikeway Improvement pilot project, starting approximately February 1, 2020; establishing Class II, Class III and Class IV bicycle facilities on Page Street; adding a peak period right-tur…19 Nov 2019 · SFMTA Board · ADOPTED — 7 ayes
- ESTABLISH – SIDEWALK BIKE SHARE STATION Steiner Street, east side, from 20 feet to 72 feet south of California Street (51-foot station) (Supervisor District 2) Laura Stonehill, [staff email removed — see the order] Propo…18 Oct 2019 · Engineering hearing · Approved by City Traffic Engineer for implementation. Public Comments: Comments received in support and opposition.
Construction on these street segments
Construction start and end as each department publishes them; a dot where only one is published. 3 other projects on these street segments publish no construction dates.
8 other projects on these street segments
- Page Slow StreetSFMTA · Planning · 31 shared street segments
- Mission District Sewer Rehabilitation (VLLD2B)Public Works · Design · 3 shared street segments
- Wiggle Neighborhood Green CorridorSFMTA · Completed · 3 shared street segments
- PW Contract 35 Traffic Signal UpgradePublic Works · Construction · 1 shared street segment
- PW StreetResurfacingPro-BBSR Pavement Prese FY 26-27Public Works · Construction · 1 shared street segment
- Various Locations Sewer Replacement No 29Public Works · Design · 1 shared street segment
- Golden Gate Park Access and Safety ProgramSFMTA · Legislated · 1 shared street segment
- Slow StreetsSFMTA · Construction · 1 shared street segment
How we built this: About the Data